Tuesday's midterms were the first national election in which data centers were a top-tier issue, and the industry lost ground in a number of key jurisdictions. Democrats who campaigned on moratoriums or tighter rules won the governorships in Texas, Ohio and Georgia, three of the country's most important data center markets (IBTimes). At the local level, at least 29 jurisdictions approved measures to ban or restrict data centers.
The results will affect everything from entitlements and incentives to utility costs. The industry already feels it. Speaking at a Wall Street Journal conference the day after the election, Meta President Dina Powell McCormick said building data centers is now "going to be harder," and added that hyperscalers are asking whether they need to build outside the United States (Gizmodo, citing the WSJ).
For those developing projects and considering new site locations, how will the path forward be charted?
Large Data Center Markets in Flux
Texas. Texas is the single most consequential result for the industry. SemiAnalysis estimates Texas accounts for 41% of new U.S. data center capacity expected in 2028, and Democrat Gina Hinojosa defeated Gov. Greg Abbott after campaigning for a moratorium on new construction (IBTimes).
Hinojosa was explicit on the trail. In an October video she said, "When I am governor I will issue a moratorium — a ban — on all data center approvals" until the Legislature passes protections (Texas Tribune via KFOX). Her stated priorities for lawmakers include union labor requirements and protections for community water supplies. Worth remembering: Abbott himself had already ordered a pause on some approvals in August, so the incoming administration is extending a freeze, not inventing one.
Texas also elected Democrat James Talarico to the U.S. Senate. He framed his win over Ken Paxton as a rebuke of a senator who would "sell off Texas land to his data centers" (CBS News). Talarico opposes a full moratorium, but his plan calls for ending the state sales tax exemption and making large users pay for their own grid infrastructure (San Antonio Current).
Ohio. Ohio now has a governor-elect who campaigned on a conditional moratorium. Amy Acton's plan would require projects to cover 100% of their utility costs, build with union labor and operate with full transparency. Her line on the trail was "Ohio is open for business, but we are not up for sale" (Dayton Daily News). She has also pledged to end data center non-disclosure agreements in the state (Tribune Chronicle). The Acton administration will be counterbalanced by a Republican legislature, though Democrats picked up seats in both chambers and ended the GOP's supermajority in the Ohio House, limiting its ability to override vetoes (Ohio Capital Journal).
The governor's appointment power matters as much as any executive order. Ohio's next governor appoints all five members of the Public Utilities Commission (PUCO), which sets rates and the terms under which data centers connect (Ohio Capital Journal). PUCO decisions could affect not only data center development but infrastructure and industrial projects more broadly.
In the U.S. Senate race, Sherrod Brown unseated Jon Husted after repeatedly attacking what he called "out-of-control tax breaks" for data centers (Sherrod Brown). That puts Ohio's data center sales tax exemption under pressure from both Columbus and Washington.
Georgia. Keisha Lance Bottoms became the first Black woman elected governor of a U.S. state, and Democrats also won the races for lieutenant governor, attorney general and secretary of state (News4JAX). Bottoms ran on a temporary statewide pause on new data center construction. The governor-elect told a Savannah audience, "Georgia is currently No. 1 in the country for data centers. We need to pause" (WTOC). She has also said a pause would be among her first priorities and that she is aligned with the data center proposals of Public Service Commissioner Peter Hubbard, a Democrat elected to the PSC in 2025 (WABE).
Unlike Ohio, Georgia will have a split legislature. Democrats flipped the state House, while Republicans held the Senate (Atlanta News First). That may make restrictions easier to advance than in the past: Georgia's 2026 session produced bipartisan bills to rein in data centers, but none reached the governor's desk (WABE). A pause by executive action alone may be legally narrow, so watch whether Bottoms and the PSC move together on rates and interconnection.
Local moratoriums: voters said no by wide margins
Ballotpedia tracked 41 data center measures across 10 states on Tuesday, 28 to restrict development and 13 to facilitate it (IBTimes). Nearly every counted measure we've seen went against data centers. The lone reported win for supporters came in Harwood, North Dakota (AIStockWire, citing Stateline).
Sources: Fortune for Perry, Trenton, Wilmington, Sunbury and Ashville; IBTimes for Granville and Hubbard. Results were unofficial as of Wednesday.
Two lessons stand out from the local measures. First, the 25 MW threshold is becoming a template, and it targets hyperscale campuses specifically. Second, some of these measures reach projects already in motion, which raises the risk profile for any site that hasn't secured final local approvals. Not every measure is binding, and several will likely end up in court, but the political signal sent to local leaders and data center developers is significant.
The states still saying yes
While Texas, Ohio and Georgia recalibrate, a group of mostly Southern and Appalachian states remains openly pro-data center. Their leaders were not on Tuesday's ballot, and their message to developers hasn't changed.
West Virginia. Gov. Patrick Morrisey has been the most aggressive recruiter in the region. The 2025 microgrid law (HB 2014) created certified data center and microgrid districts and moved siting decisions to the state level. In August, Morrisey released a seven-point responsible development framework built on the principle that "All West Virginians must directly benefit from data center revenue" (E&E News). The plan would dedicate half of hyperscale revenue to reducing and eventually eliminating the state income tax (Fox News). The Mason County Monarch campus, now under Nscale, is a flagship project.
Louisiana. Gov. Jeff Landry has tied his administration to Meta's Hyperion campus in Richland Parish, now planned at 5 GW and more than $50 billion. Landry said the commitment "puts Louisiana at the center of America's future in artificial intelligence" (Louisiana Economic Development). His June 2026 executive order paired continued recruitment with a ratepayer protection framework, and the state's 20-year sales tax exemption covers facilities built before 2029 (UPI).
Mississippi. Gov. Tate Reeves landed xAI's $20 billion Southaven project in January, the largest corporate investment in state history, and called it "record-shattering" (WDAM). Mississippi's 2024 incentive package exempts qualifying facilities from sales, use, corporate income and franchise taxes (Introl).
Others to watch. North Dakota was the one place on Tuesday where voters sided with development, rejecting stricter review of large industrial projects in Harwood. We'd also keep an eye on the remaining Republican-led states that have avoided moratorium talk, though the bipartisan nature of local opposition means no state is immune.
The common thread in the pro-development states is that each has added ratepayer protections to its pitch. Even the friendliest governors now understand that "yes" has to come with a guarantee that residents won't pay for the grid.
What this means for developers and communities
Tuesday didn't end data center development in America, but the map for development became more complicated. We believe the following factors will shape site selection and development in the years ahead:
• Pay your own way on power. Most winning candidates, Democrat or Republican, ran on the principle that residents should not subsidize data center grid costs. Being able to answer how power infrastructure is secured, financed and developed will be increasingly important.
• Plan for disclosure. NDAs are a hot-button political issue. Firms should operate under the assumption that company names and project facts will be made public.
• Lead with community benefit agreements and incentives strategy. Local governments now have the leverage, and ballot measures give residents a veto that didn't exist two years ago. Discussing a community benefit agreement and an incentives strategy early is critically important.
• Diversify the site search. For new projects, it is wise to widen data center site searches to new states. Examples include West Virginia, Louisiana and Mississippi, which offer state-level support that Texas, Ohio and Georgia may not provide in the near term.
• Watch the 2027 sessions closely. New governors will set the tone, but legislatures and utility commissions will write the rules. Early engagement is the best risk management available.
The political environment will remain an important factor in data center development, and success will require new approaches from developers and communities alike. If you're a developer, site selector or community leader working through what these results mean for a specific project, Strategic Development Partners is glad to help.
Sources
• IBTimes: America's AI Boom Faces A New Obstacle
• Gizmodo: Meta's president on midterm results
• Texas Tribune via KFOX: What happens to Texas data centers now?
• CBS News: Talarico on his Senate win
• San Antonio Current: Talarico rejects a moratorium
• Dayton Daily News: Acton's conditional moratorium
• Tribune Chronicle: Ramaswamy, Acton on data centers
• Ohio Capital Journal: Democrats break Republican supermajority in the Ohio House
• Ohio Capital Journal: Next governor will select regulators
• Sherrod Brown: Tax breaks for data centers
• News4JAX: Bottoms' election as governor
• WTOC: Bottoms calls for a data center pause
• WABE: Data centers in the Georgia governor's race
• Atlanta News First: Georgia Democrats flip state House
• WABE: Bottoms and Jackson at the Georgia Chamber
• Fortune: Ohio's data center ballot measures
• AIStockWire: Data center ballot votes
• E&E News: West Virginia's data center plan
• Fox News: West Virginia income tax plan
• Louisiana Economic Development: Meta in Richland Parish
• UPI: Meta's Louisiana data center cost